East Milham Avenue Nighttime Milling and Paving
South Westnedge Avenue to Portage Road
On Tuesday, August 10 at 6:30 PM, edge trimming and final paving operations will begin on East Milham Avenue from South Westnedge Avenue to Portage Road and will continue through the overnight hours. The nighttime paving work will occur over two nights; however, work will cease by 7 AM the following morning. All construction schedules are dependent on favorable weather conditions.
Motorists can expect traffic delays in this area and should seek an alternate route. Please remember to drive with caution and watch for individuals engaged in work. The East Milham Avenue Reconstruction project is expected to be complete by August 27, 2021.
For more information, call the Department of Transportation & Utilities at (269) 329-4422.